ENERGY EFFICIENCY & CONSERVATION BLOCK GRANT FUNDS AWARD NO. DE-SC0001927 |
|||
PROJECT STATUS UPDATED: 1/11/2011 |
|||
EECBG Project Activity |
Grant Amount |
Project Amounts |
Status |
Project Activity #1 – HVAC System Retrofit at Babcock Street Police Department |
$251,017.00 |
|
|
Retrofit existing aging, inefficient HVAC system at Police Department at Babcock Street with new 50-ton air-cooled chiller with 260-ton-hours of thermal storage capacity. |
|
|
|
Engineering Services Frazier Engineering, Inc. Melbourne, FL |
|
$14,640.00 |
Completed |
Construction Contract Construction Management Associates, Rockledge, FL |
|
$240,680.00 |
Construction to begin March 2011 |
Project Activity #2 – Solar Thermal Water Heaters at Fire Stations |
$42,000.00 |
|
|
Retrofit existing electric hot water heaters with solar thermal powered water heaters |
|
|
|
Engineering Services Frazier Engineering, Inc. Melbourne, FL |
|
$13,800.00 |
Under Design |
Construction Contract |
|
|
Bid in Jan 2011 |
Project Activity #3 – LED Lighting Replacements |
$196,868.00 |
|
|
Retrofit existing High Pressure Sodium (HPS) and Metal Halide (MH) bulbs with Light Emitting Diodes (LED) lamps at various locations throughout the city. |
|
|
|
Engineering Services Frazier Engineering, Inc. Melbourne, FL |
|
$21,500.00 |
Under Design |
Construction Contract |
|
|
|
Project Activity #4 – Energy Efficient Roof Replacements |
$188,615.00 |
|
|
Lake Washington Surface Water Treatment Plant Replace portion of existing non-energy efficient roof with Title 24 Compliant Energy Star-Rated roofing system. |
$81,200.00 |
|
|
Engineering Services Frazier Engineering, Inc. Melbourne, FL |
|
$12,800.00 |
Completed |
Construction Contract The Roof Authority, Inc., Fort Pierce, FL |
|
$54,710.00 |
Under Construction |
Front Street Civic Center Replace existing non-energy efficient roof with Title 24 Compliant Energy Star-Rated roofing system. |
$107,415.00 |
|
|
Engineering Services Frazier Engineering, Inc. Melbourne, FL |
|
$13,800.00 |
Completed |
Construction Contract The Roof Authority, Inc., Fort Pierce, FL |
|
$60,347.00 |
Construction to begin January 2011 |
Project Activity #5 – Long Term Strategic Energy Plan |
$135,000.00 |
|
|
Phase 1 - Energy Efficiency & Conservation Strategy (EECS) Grant Requirement to obtain funding. Identifies municipal retrofit projects to be funded by the EECBG grant. EECS performed by Frazier Engineering, Inc. |
$25,000.00 |
$25,000.00 |
Completed |
Phase 2 - Municipal and Community Sustainability Overall long term plan to focus on energy reductions for municipal operations in addition to community-wide energy reduction. Will include energy audits of municipal facilities and explore idle reduction, bike and pedestrian ways, community outreach and incentive programs for residential and commercial properties. |
$110,000.00 |
|
Conceptual Planning Underway |
Total Grant Amount |
$813,500.00 |
|
|
Acknowledgement: This material is based upon work supported by the Department of Energy under Award Number DE-SC0001927.
This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference3 herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.