Fire Protection System Permit Requirements
   
 

The following list of requirements are for Fire Protection System Permits and are in addition to all other requirements for Commercial Permits.

 
 

Fire Alarm System

 
 
 Note 2 sets of Design Plans, signed/sealed if over $5,000.00 valuation
 Note 2 sets of Specifications / Technical Documents
 
  Fire Sprinkler System  
 
 Note 2 sets of Design Plans, signed/sealed for over 50 heads
 Note 2 sets of Hydraulic Calculations
 Note No Permit required for relocating up to 3 heads
 
  Fire Suppression System  
 
 Note 2 sets of Design Plans, signed/sealed for over $5,000.00 valuation
 Note

2 sets of Specifications / Technical Documents

 
  Exhaust Hoods  
 
 Note 2 sets of Design Plans, (pre-engineered) not signed & sealed
 Note 2 sets of Specifications / Technical Documents (pre-engineered)
 Note 2 sets of Construction Plans (Site Built) signed & sealed
 
  Standpipe System  
 
 Note 2 sets of Design Plans, signed/sealed for over $5,000.00 valuation
 Note 2 sets of Hydraulic Calculations
 
  Fire Pump  
 
 Note 2 sets of Design Plans, signed/sealed for over $5,000.00 valuation
 Note 2 sets of Hydraulic Calculations
 
  Fire Protection System Demolition  
 
 Note 2 Letters of Intent (all removals / disconnects)
 Note Scope of Work Statement
 
  Paint Spray Booth  
 
 Note 2 sets of Design Plans, (pre-engineered) not signed & sealed
 Note 2 sets of Specifications / Technical Documents (pre-engineered)
 Note 2 sets of Construction Plans (Site Built) signed/sealed
 
  Tank Installations - Any Type  
 
 Note 2 sets of Design Plans, (pre-engineered) not signed & sealed
 Note 2 sets of Specifications / Technical Documents (pre-engineered)
 Note

2 sets of Construction Plans (Site Built) signed/sealed

 
  Tank Removal - Any Type  
 
 Note 2 sets of Site Plans
 Note

2 Letters of Intent

 Note Scope of Work Statement
 

  Return to Melbourne Home Page